Pre-Shipment Inspection for Crushing and Mineral Processing Equipment: A Buyer’s Checklist

For most equipment orders, the balance payment is released after inspection. That makes inspection the last point where a problem can be fixed at the supplier’s cost and on the supplier’s schedule. This note lists what to agree and what to check, for buyers who inspect in person, through an agent, or by video.

One limit to keep in mind: a factory inspection confirms that the machine was built as specified. It does not prove how the machine will perform on your ore. Capacity and product size depend on feed material and are confirmed at commissioning, not on the factory floor.

1. Agree the inspection scope before production starts

Inspection is easy when it is written into the contract, and hard when it is raised at the end. Before production begins, agree in writing:

  • Which drawings and specification the machine is built to, and which version is approved.
  • Which points you will witness (for example: key material certificates, assembly, no-load run, packing).
  • Whether the inspection is online, on site, or by a third-party inspection company, and who pays for it.
  • What happens if an item fails: it is corrected and re-inspected, and the balance is not released until the item is closed.

2. Ask for documents first

Before travelling or scheduling a video call, ask for the documents. Missing paperwork is often the first sign of a problem.

  • Approved general arrangement drawing and the parts list.
  • Material reports for the parts that carry load or wear: liners, jaw plates, shafts, castings, main welded structures. Ask for the material grade and the chemical analysis, not only a statement that the part is “high manganese steel”.
  • Motor and reducer nameplate data, and the brands of bearings, motors, reducers and electrical parts if they were specified in the contract.
  • Painting specification and, for welded structures, the welding inspection record if one was agreed.

3. Visual and dimensional check

  • Nameplate against contract: model, motor power, voltage and frequency. A motor built for the wrong supply voltage or frequency is a common and expensive mistake.
  • Dimensions against drawing: overall size, mounting holes, inlet and outlet flanges, and the positions where your chutes, feeders or conveyors connect.
  • Welds and structure: continuous welds, no cracks or undercut, no visible distortion on large fabricated parts.
  • Machined and bolted parts: parts fit without forcing, bolts are the specified size and grade, and spare or loose parts are listed.
  • Surface protection: paint is complete and machined surfaces are protected against rust for sea transport.

4. Check by equipment type

EquipmentCheck at inspection
Jaw crusherJaw plate material and fit; toggle plate and seat; flywheel and bearing assembly; range of discharge setting adjustment; lubrication points.
Cone crusherMantle and concave fit; lubrication system (pump, filter, cooler, pressure); hydraulic adjustment and overload release; dust seal; rotation direction of the drive.
Ball millShell and head welds; liner type and fit; trunnion bearings and lubrication; girth gear and pinion contact and backlash; drive alignment; manhole sealing.
Vibrating screenExciter and spring condition; side plate welds; screen opening against the specification; for double-motor screens, the two motors must rotate in opposite directions.
Belt conveyorBelt width, grade and number of plies; idlers turn freely by hand; pulley lagging; tensioning device; drive and guards.
Flotation cellTank welds; impeller and stator material; shaft straightness; motor power; seals and lining.

5. No-load run test

Most factories can run the machine empty. Agree the duration in advance and check:

  • Rotation direction matches the direction arrow on the machine.
  • Noise and vibration are steady, without knocking or sudden changes.
  • Bearing temperature rise stays stable and does not keep climbing.
  • No oil or grease leaks at seals, covers or pipe joints.
  • Motor current is steady and within the nameplate rating.

A no-load run shows that the machine is assembled correctly. It does not show capacity under load.

6. How to inspect by video

Online inspection works when the video is planned. A casual walk-around does not prove much.

  • Send your checklist and the drawing before the call so the supplier can prepare.
  • Put a card with your order number and the date in the shot, so the video clearly shows your machine.
  • Ask for close-ups of the nameplate, welds, liners, bearings and any point on your checklist.
  • Ask them to measure key dimensions with a tape or caliper in the frame.
  • Ask for the no-load run on camera, with sound, and record the call.

7. When to inspect on site, or use a third party

For high-value or custom-built equipment, an on-site visit is worth the cost. If you cannot travel, a third-party inspection company can check against your checklist and send a report with photos. Give them the contract, drawings and checklist, and agree beforehand what they may approve and what they must refer back to you.

8. Packing and loading

  • The packing list matches the contract, including spare parts and tools.
  • Each package is marked with your order number and a package number.
  • Loose parts are labelled so site crews can match them to the drawing.
  • Take photos while loading, and record the container and seal numbers.

9. If something fails

Record the item with photos, agree the correction and the date in writing, and re-inspect that item. The balance payment should follow the terms of your contract and the closed inspection list, not the shipping date.

Quick checklist

  • Inspection scope and failure handling written into the contract
  • Drawings, material reports and nameplate data received
  • Nameplate, dimensions and welds checked
  • Equipment-specific points checked
  • No-load run witnessed, with duration agreed
  • Packing list, marks and loading photos confirmed

Inspection with CNEIG INDUSTRIAL

We support online and on-site inspection before delivery. If you are comparing offers or preparing an order, send us the equipment list and your inspection requirements, and we will arrange the inspection plan with the manufacturer before production starts.